First Conduits & Completion of East Side Retaining Wall

Filling in the east side retaining wall the top of which will be approximately ground level leaving about 10 feet below ground. The retaining wall itself comprises about 35 yards of concrete which, together with the pillars, means some 50 yards of concrete have gone in so far and we have not yet started with the foundations.




The completion of the east side retaining wall involved the installation of the first conduits for electricity, telephone and cable. I would not have thought that the TV cable would be one of the first items on the project list, but there you go...